Flame Arrester Specification Checklist for Industrial RFQs

2026-11-19

Two quotes can list the same flange size and describe different duties. One supplier may use an air flow curve, while another may quote a pressure drop for the actual process vapor. The offered configurations, installation limits, and supporting documents can also differ. At BasCo, we suggest giving every bidder the same application data and a clear list of what to return with the quote.

A complete flame arrester RFQ gives each supplier the same installation and operating conditions. It also asks for model-specific evidence so engineering can verify the application and procurement can compare quotes on the same basis.

What Should You Include in a Flame Arrester RFQ?

Prepare one datasheet per equipment tag. Give the datasheet a revision number and list the supporting drawing revisions. Ask bidders to identify the offered model and configuration, then mark each item Confirmed, Deviation, or Pending and cite the relevant document or drawing.

Flame arrester specification checklist

RFQ itemBuyer providesSupplier returns
Duty and locationTag, protected equipment, service description, and marked piping drawing.Offered model, protection classification, installation orientation and limits of use.
Gas or vaporComposition and expected range, concentration basis, confirmed gas group if available.Applicable gas group for the offered configuration and any unresolved media assumptions.
Operating envelopeOperating pressure and temperature ranges, and project-defined cases requiring review.Applicable pressure and temperature limits for the offered configuration, with supporting references.
Flow and pressure dropFlow case, direction where applicable, units, reference conditions, and allowable device pressure drop.Model-specific curve or sizing sheet, quoted pressure drop by case, and the evaluation basis.
Materials and connectionsLine size, connection standard and rating, media compatibility requirements, and space constraints.Housing, element and seal materials, connection details, and a general arrangement drawing.
Evidence and scopeApplicable standards and editions, required approvals, document schedule, quantities, and spares.Applicable evidence and referenced attachments, technical deviations, exclusions, and delivery scope.
Flame arrester RFQ package showing an equipment tag datasheet, an installation sketch, and matching operating cases on the process data and supplier response sheets.
Use the same tag, document revisions, and operating cases across the RFQ package.

How Should You Describe the Installation and Protection Duty?

Show the proposed arrester location on a P&ID or piping sketch. Identify whether the device sits at an open termination or within the line. Mark the equipment to be protected, the potential ignition side or sides identified by the project, and the intended flow direction. For in-line service, include relevant pipe lengths, diameters, bends, and restrictions in the documented layout.

Record the protection duty established by the project engineering team and ask the supplier to identify the limits that apply to the offered model. If ignition can occur on either side, ask for evidence covering the direction or directions required. Where sustained burning is credible, communicate the project requirement and request the applicable burning classification and any associated conditions for use.

Use the guide to flame arrester installation distance to identify which piping details to bring to the technical review.

RFQ piping sketch showing the protected vessel, the in-line flame arrester location, and the potential ignition side.
Mark the arrester location, protected equipment, and potential ignition side on the RFQ drawing.

Which Process and Flow Data Should You Send?

Gas or Vapor Composition and Operating Conditions

List the expected components and their concentration ranges. State whether concentrations are on a volume, mole, or mass basis. Provide the normal operating pressure and temperature ranges, plus relevant startup, shutdown, or upset cases defined by the project. For each pressure, state whether it is absolute or gauge. Mark unresolved media or gas group information as pending and give it an owner and a due date.

Flow Basis and Allowable Pressure Drop

Give each relevant flow case its own row. Include the gas or vapor, flow direction where applicable, pressure and temperature at the agreed reference point, and the allowable pressure drop across the arrester at that flow. For standard or normal volumetric flow, write out the reference temperature and absolute pressure. Ask the supplier to state the basis used for each curve or calculation.

Materials, Connections, and Maintenance Access

Flag condensate, corrosive constituents, or deposits the project expects to encounter. Specify connection size, standard, rating, and facing where applicable. Ask the supplier to identify the housing, flame arrester element, and seal materials separately and show the space needed to remove the element. For a deeper review, see our flame arrester materials guide.

Which Documents Should the Supplier Return with the Quote?

Request an offered-model datasheet, a flow curve or sizing sheet, a preliminary general arrangement drawing, and a deviation list. For each applicable approval or test requirement, ask for the evidence and attachments relevant to the offered size and configuration. Match the model designation and applicable limits in the documents against the RFQ duty and drawing revision.

State the standard edition required by the project. ISO/IEC 80079-49:2024 addresses performance, testing, and limits of use for flame arresters within its scope. Have project engineering review any differences between the specified and offered editions, as well as any service outside the standard’s scope. See our flame arrester selection guide under ISO/IEC 80079-49 for more context.

Set the document schedule in the RFQ. Identify the evidence needed for technical evaluation at bid stage and the documents due after order. Final drawings, installation and maintenance instructions, and production or material records can be listed with their contractual submission milestones.
Flame arrester datasheet, drawing, and supporting evidence shown side by side, with the same equipment tag and offered configuration highlighted on each document.
Check that the datasheet, drawing, and supporting evidence identify the configuration offered for the tag.

How Can You Compare Two Flame Arrester Quotes?

Suppose one bidder sends a catalog air curve and a second gives a pressure drop for the process vapor. Ask both bidders to complete the same row for the same RFQ case. Record the result only after the bidder identifies the offered configuration and confirms the flow basis and equipment included in the evaluation.

Illustrative comparison for the same equipment tag and flow case

CheckBidder ABidder BBuyer follow-up
Pressure-drop evidenceCatalog air curve.Process-vapor result with an unspecified flow basis.Request both results for the same case, with units, reference conditions, and document references.
ConfigurationProduct family identified.Specific model quoted.Confirm both complete model codes and the configurations covered by the data.
Supply boundaryArrester listed.Arrester with a vent valve listed.Confirm supply scope. Where the duty requires the combination, request evidence for the offered assembly.

Keep a technical deviation log by tag. Include the original requirement, the proposed deviation, the vendor’s evidence, and the project engineer’s disposition. After technical review, compare price, lead time, and spares against the agreed scope.

Two flame arrester quotes compared using the same gas or vapor, flow reference conditions, and allowable pressure drop.
Put both quotes on the same flow and pressure-drop basis before comparing them.

Which BasCo Flame Arrester Models Can You Review?

Use the product pages to review the available configurations for your documented duty. Confirm the applicable limits and evidence for the specific model and configuration during technical review. For background on types and applications, see our flame arrester engineering guide.

What Else Should You Check Before Issuing the RFQ?

Can I request a quote before the gas group is confirmed?

Mark the request as budgetary or preliminary. Record the unresolved gas group, provide the composition information available, and ask the bidder to identify assumptions. Resolve the pending item before technical approval.

What if a supplier cites a different edition of the standard?

Ask for the exact cited edition, the offered-model documents, and a written deviation. Submit those records for review against the project requirements and applicable approval rules.

What should I request when a flame arrester is quoted with a PVRV?

State the required assembly and its relevant venting cases. Request performance data for the offered combination, with the included equipment, flow direction, and test or calculation basis clearly identified.

Ready to Send Your Flame Arrester RFQ?

Send BasCo your equipment tags, process conditions, installation drawings, and required documents. Flag any pending data so we can identify what needs clarification for a technical quotation.

About the Author | Expert Contributor
Eric